Project Status

Starting Jun 21 , 2017 (82 day project)

Project Budget

₹ 1,80,000

Task Status

Ongoing Tasks Estimated Completion
Bathroom-1 Aug 16 , 2017
Kitchen Aug 16 , 2017
Master Bathroom Aug 16 , 2017
Utility Room Aug 16 , 2017
Civil Work Jul 02 , 2017
Electrical Work Aug 18 , 2017
A.c Work Jul 03 , 2017
False Ceiling Aug 02 , 2017
Flooring Aug 26 , 2017
Paint And Polish Aug 19 , 2017
Door And Windows Work Sep 10 , 2017
Wood Work Sep 10 , 2017

Payments

Due
Jul 28 , 2017 Due ₹ 4,00,000
Aug 28 , 2017 Due ₹ 4,00,000
Oct 02 , 2017 Due ₹ 2,78,615
Paid
Jun 20 , 2017 ₹ 4,00,000