Demolish of 4BHK

Task started on Dec 01 , 2018. Expected completion was December 09 , 2018

Costs

Labour Costs

Room demolition Demolition and dismantling of site as per drawings, using suitable tools and machines, causing no harm to remaining walls. This includes debris removal. 1276 SQ.FT ₹ 30/SQ.FT Total: ₹ 38,280
Misc. demolition Demolition and dismantling of site as per drawings, using suitable tools and machines, causing no harm to remaining walls. This includes debris removal. 661 SQ.FT ₹ 30/SQ.FT Total: ₹ 19,830

Major Products

No materials specified.